{"id":5403,"date":"2020-11-19T06:23:22","date_gmt":"2020-11-19T05:23:22","guid":{"rendered":"https:\/\/www.bachy-soletanche.com.hk\/?post_type=avada_portfolio&p=5403"},"modified":"2024-07-24T09:47:36","modified_gmt":"2024-07-24T07:47:36","slug":"hkia-contract-3802-apm-and-bhs-tunnels-and-associated-works","status":"publish","type":"avada_portfolio","link":"https:\/\/www.bachy-soletanche.com.hk\/offer-portfolio\/hkia-contract-3802-apm-and-bhs-tunnels-and-associated-works\/","title":{"rendered":"HKIA Contract 3802 – APM and BHS Tunnels and Associated Works"},"content":{"rendered":"
The Project constructs a combined 1.8km long eight cell tunnel structures for the automatic people mover (APM) and baggage handling system (BHS) systems, which facilitate travelers to move between the new Third Runway Concourse and the expanded Terminal 2.<\/p>\n<\/div>
Scope of Works<\/span><\/p><\/h2><\/div> Construction of reinforced slurry wall panels under low headroom in the area within existing CSM and Seawall, and land cement soil mixing panels. Owner:<\/span> Engineer:<\/span> General contractor:<\/span> Period of works:<\/span>
\n– Reinforced slurry wall panels: (a) 492 nos., (b) 1.2m thick, (c) excavation volume 34,585m\u00b3
\n– Land cement soil mixing panels: (a) 210nos., (b) dimension 2.8m x 1.0m, (c) excavation volume 8,232m\u00b3<\/p>\n<\/div><\/div><\/div>
\nAirport Authority Hong Kong<\/span><\/b><\/p>\n<\/div>
\nAecom Asia Company Limited<\/span><\/b><\/p>\n<\/div>
\nGammon Construction Limited<\/span><\/b><\/p>\n<\/div>
\nNov. 2020 to Mar. 2022<\/span><\/b><\/p>\n<\/div><\/div><\/div>