Project Description

The Project constructs a combined 1.8km long eight cell tunnel structures for the automatic people mover (APM) and baggage handling system (BHS) systems, which facilitate travelers to move between the new Third Runway Concourse and the expanded Terminal 2.

Scope of Works

Construction of reinforced slurry wall panels under low headroom in the area within existing CSM and Seawall, and land cement soil mixing panels.
– Reinforced slurry wall panels: (a) 492 nos., (b) 1.2m thick, (c) excavation volume 34,585m³
– Land cement soil mixing panels: (a) 210nos., (b) dimension 2.8m x 1.0m, (c) excavation volume 8,232m³

Owner:
Airport Authority Hong Kong

Engineer:
Aecom Asia Company Limited

General contractor:
Gammon Construction Limited

Period of works:
Nov. 2020 to Mar. 2022

0+
Years in Hong Kong
0M$+
Yearly Turnover
0+
Projects Completed
0+
Employees

You have a project ?

Bachy Soletanche is the Leading Specialist Geotechnical and Foundation Contractor, contact us without delay.

You have a project ?

Bachy Soletanche is the Leading Specialist Geotechnical and Foundation Contractor, contact us without delay.