Project Description
The Project is developed in 2 Phases. Phase 1 contains about 270,000 sq. ft. of office space, 340,000 sq. ft. of retail, dining and entertainment spaces, and about 900 parking spaces, while Phase 2 provides an addition of about 390,000 sq. ft. of office space, 600,000 sq. ft. of retail space, and an underground connection to the Central MTR Station. It will be a world-class iconic landmark of Hong Kong.
Scope of Works
Construction of foundations and retaining structures for excavation and lateral support works. Foundations include large diameter bored piles, while retaining structures include diaphragm walls and clutched pipe piles installed with steel stanchions. Some diaphragm walls are constructed under low headroom (6m worst).
– Diaphragm walls: (a) 1.2m & 1.5m thick, (b) excavation area 38,000m2
– Bored piles: (a) 31 nos., (b) diameter 2m to 3.3m, (c) total length 1,741m
– Clutched pipe piles: (a) 9 nos. (b) diameter 813mm, (c) total length 399m
Owner:
Henderson Land Development Company Limited
Engineer:
Ove Arup & Partners Hong Kong Limited
General contractor:
Vibro (H.K.) Ltd.
Period of works:
Jul. 2022 to Jun. 2024