Project Description
The development comprises five blocks of 34-storey residential buildings which are supported by 109 number Large Diameter Bored Piles via 5 numbers of pile caps.
Scope of Works
Construction of foundations, ELS works and pile caps. Foundations include large diameter bored piles, while retaining structures include installation of sheet pile walls, strut and waling.
– Bored piles: (a) 109 nos., (b) diameter Ø2.8m to Ø3.0m, (c) total length ~6,700m
– ELS works: (a) Installation of sheet pile, strut & waling (b) total weight ~2,500 tons.
– Pile Caps: (a) Concrete ~ 30,000m3 (b) Reinforcement ~10,000 tons.
– Pile Removal: (a) abandoned H-pile removal ~ 100 nos
The scope of the foundation works includes the installation of 109 nos Large Diameter Bored Piles with bellout in diameter of Ø2.8m, Ø3.0m & Ø3.3m, excavation lateral support (ELS) works, pile cap construction and removal of abandoned H piles.
Owner:
Hong Kong Housing Authority
Engineer:
Hong Kong Housing Authority
General contractor:
Bachy Soletanche Group Limited
Period of works:
Feb. 2024 to Present